Analysis of Rate in Estimating and Costing
Syllabus: Analysis of Rate (6 Hours)
6. Analysis of Rates (6 hours)
6.1 Importance and purpose of rate analysis
6.2 Data required for rate analysis
6.3 Factors affecting rate analysis
6.4 Prevailing rate analysis norms and district rates in Nepal
6.5 Analysis of rate
6.5.1 Building works: Brickwork, concrete work, reinforcement work, woodwork, plasterwork, and flooring work
6.5.2 Road works: Earthwork in excavation/filling using equipment; Gabion, stone masonry, plum concrete, and pavement works
6.5.3 Sanitary and water supply works: Wash basin; commode and pan; pipes and fittings
Analysis of Rate Notes
1. What is Rate Analysis?
The method of determining the rate per unit of a particular item of work, considering the cost and quantities of materials, cost of labour (skilled and unskilled), hire of tools and plants, and contractor’s profit, etc., is known as Rate Analysis.
The rate of material is usually taken as the rate delivered at the site of work and includes the first cost (cost of origin), cost of transport, taxes, etc. If materials are to be carried from a distant place, more than 8 km, the cost of transportation is also added. The rate of materials and labour vary from place to place, and therefore the rate of a different item of work also varies from place to place.
2. Purpose of Rate Analysis
The purpose of rate analysis can be summarized as follows:
- To work out the actual cost per unit of an item.
- To work out the economical use of materials.
- To work out the cost of extra items which are not provided in the contract documents (Bill of Quantities – BOQ).
- To revise the schedule of rates due to changes in construction technique.
3. Requirement of Rate Analysis
- Correct information of the market rate of materials.
- Correct information of the rate of various categories of labour.
- Output of labour.
- Knowledge, rate, and outturn of various types of plant to be used in the construction work.
- Up-to-date knowledge of construction.
- Standards norms.
4. Factors Affecting Rate Analysis
- Specification of work and quality of materials.
- Proportion of mix (concrete or mortar).
- Construction facilities and availability of materials, tools, and plants.
- Location of site.
- Cost of labours and their availability.
- Facilities available for transportation of materials and labours to the site.
- Condition of road to the worksite.
- Overhead charges.
The rate of a particular item of work depends on the following:
- Specification of different items of work and materials to be used.
- Quantities of materials and their rates, number of different types of labours (skilled/unskilled).
- Location of work site, means of communication, distance of site from the sources of materials, rates of transportation, availability of workers.
- Availability of tools and plants, different types of equipment for different operations as per specification.
- Profit and overhead expenses of contractors.
5. Importance of Rate Analysis
- The process of doing analysis gives a clear picture of the various types of labours and materials required for completing the particular work.
- It can be used frequently to settle the disputes between contractor and client about the item not included in the original estimate.
- It can be used for the compensation by insurance.
Material Estimate
Note (Dry Mix / Wastage Norms)
- In concrete mix: To get dry mix (Cement + Sand + Aggregates), increase 50% to 55% of wet mix.
- In mortar mix: To get dry mix (Cement + Sand), increase 30% to 35% of wet mix.
- In plastering works: Firstly, increase 25% for filling in between joints and irregular surface. In case of ceiling and concrete surface (plain surface), only 10% – 15% increase of wet mix to get total wet mix. Then, to get dry mix (Cement + Sand), increase 30% to 35% of wet mix.
- In case of stone works: To get required stone, 15% – 20% increase of total works due to wastage and dressing. Volume of dry mortar mix = 30% to 40% of stone masonry.
- In RCC work: To get reinforcement: 1-3% of volume of RCC. Loss during cutting (but no lap and chair length included) = 5%. Binding wire: 10 Kg per quintal.
Calculate the Quantities of Materials Required for the Following Items of Work
Volume of brick work = 48.5 m³. Assume brick size = 230mm x 110mm x 55mm; mortar thickness = 10mm; so brick size with mortar = 240mm x 120mm x 65mm.
No. of bricks required $= \dfrac{\text{Vol. of brick work}}{\text{Vol. of one brick with mortar}} = \dfrac{48.5}{0.24 \times 0.120 \times 0.065} = 25908.11 \approx 25909$ Nos.
Add 5% wastage $\therefore$ Brick required $= 1.05 \times 25909 = 27205$ Nos.
Volume of wet mortar = Total brick work – Actual vol. of brick (without mortar) $= 48.5 – 25908.11 \times (0.23 \times 0.11 \times 0.055) = 12.45\text{ m}^3$
To get dry vol. of mortar, 30% increase: Dry vol. of mortar $= 1.3 \times 12.45 = 16.90\text{ m}^3$
Total part of mix proportion $= 1 + 3 = 4$
$\therefore$ Required cement $= \dfrac{16.90}{4} = 4.05\text{ m}^3$ {Unit wt. of cement = 1440 kg/m³, 1 bag cement = 50 kg} $= 4.05 \times 28.8 = 116.57$ bags
$\therefore$ Required sand $= 3 \times 4.05 = 12.15\text{ m}^3$
Let water cement ratio $= 0.8$; Water $= 0.8 \times 116.57 \times 50 = 4662.8$ lit
Hence, Required: Bricks = 27205 Nos, Cement = 116.57 bags, Sand = 12.15 m³, Water = 4662.8 lit.
Total quantity of work (PCC) $= 42 \times 0.95 \times 0.15 = 5.99\text{ m}^3$
To get dry vol. of concrete mix, increase 50% to 55%: Vol. of dry mix $= 1.5 \times 5.99 = 8.99\text{ m}^3$
Total part of mix proportion $= 1 + 3 + 6 = 10$
Required: Cement $= 8.99 \times \dfrac{1}{10} = 0.899\text{ m}^3 = 0.899 \times 28.8 = 25.89$ bags
Sand $= 0.899 \times 3 = 2.697\text{ m}^3$; Aggregate $= 0.899 \times 6 = 5.394\text{ m}^3$
Water/Cement $= 0.5$; Water $= 0.5 \times 25.89 \times 50 = 647.25$ lit
PCC for RCC work $= 25 \times 20 \times 0.10 = 50\text{ m}^3$
Increase 50% for getting dry volume of mix: Vol. of dry mix $= 1.5 \times 50 = 75\text{ m}^3$
Total part of mix proportion $= 1 + 1.5 + 3 = 5.5$
Required: Cement $= 75 \times \dfrac{1}{5.5} = 13.636\text{ m}^3 = 13.63 \times 28.8 = 392.72$ bags
Sand $= 13.636 \times 1.5 = 20.45\text{ m}^3$; Aggregate $= 13.636 \times 3 = 40.91\text{ m}^3$
Water/Cement $= 0.5$; Water $= 0.5 \times 392.72 \times 50 = 9818$ lit
Mild Steel Bars (Steel Reinforcement): 1% of PCC for RCC work $= 1\%$ of $50\text{ m}^3 = 0.01 \times 50 = 0.5\text{ m}^3$ {Unit wt. of steel = 7850 kg/m³} $= 0.5 \times 7850 = 3925.00$ Kg
Binding wire $= 1$ kg per quintal $= 1 \times \dfrac{3925}{100} = 39.25$ kg
Quantity of plastering work $= 713\text{ m}^2$. Therefore, Vol. of wet mortar $= 713 \times 0.0125 = 8.91\text{ m}^3$
Firstly, increase 25% for filling in between joints and irregular surface to get total wet mix $= 1.25 \times 8.91 = 11.14\text{ m}^3$
To get dry vol. of mortar, 30% increase: Vol. of dry mortar $= 1.30 \times 11.14 = 14.48\text{ m}^3$
Total part of mix proportion $= 1 + 4 = 5$
Required: Cement $= \dfrac{1}{5} \times 14.48 = 2.896\text{ m}^3 = 2.896 \times 28.8 = 83.42$ bags
Sand $= 2.896 \times 4 = 11.58\text{ m}^3$
Let water cement ratio $= 0.8$; Water $= 0.8 \times 83.42 \times 50 = 3336.8$ lit
Quantity of work $= 110\text{ m}^2$. Vol. of brick work $= 110 \times 0.11 = 12.10\text{ m}^3$
Assume brick size 230mm x 110mm x 55mm; brick size (with 10mm mortar) $= 240$mm x 110mm x 65mm.
No. of bricks required $= \dfrac{\text{Vol. of brick work}}{\text{Vol. of one brick with mortar}} = \dfrac{12.1}{0.24 \times 0.110 \times 0.065} = 7051.28 \approx 7052$ Nos.
Add 5% wastage $\therefore$ Brick required $= 1.05 \times 7052 = 7405$ Nos.
Volume of wet mortar = Total brick work – Actual vol. of brick (without mortar) $= 12.1 – 7052 \times (0.23 \times 0.11 \times 0.055) = 2.287\text{ m}^3$
To get dry vol. of mortar, 30% increase: Dry vol. of mortar $= 1.3 \times 2.287 = 2.97\text{ m}^3$
Total part of mix proportion $= 1 + 3 = 4$
$\therefore$ Required cement $= \dfrac{2.97}{4} = 0.74\text{ m}^3$ {Unit wt. of cement = 1440 kg/m³, 1 bag cement = 50 kg} $= 0.74 \times 28.8 = 21.41$ bags
$\therefore$ Required sand $= 3 \times 0.74 = 2.22\text{ m}^3$
Let water cement ratio $= 0.8$; Water $= 0.8 \times 21.41 \times 50 = 856.40$ lit
Quantity of stone masonry $= 10\text{ m}^3$. Required: Vol. of stone $= 1.15 \times 10 = 11.5\text{ m}^3$
Vol. of dry mortar $= 40\%$ of work quantity $= 0.4 \times 10 = 4\text{ m}^3$
Total part of mix proportion $= 1 + 6 = 7$
Required cement $= \dfrac{1}{7} \times 4 = 0.57\text{ m}^3 = 0.57 \times 28.8 = 16.45$ bags
Required sand $= 6 \times 0.57 = 3.42\text{ m}^3$
W/C $= 0.6$; Required water $= 0.6 \times 16.45 \times 50 = 493.5$ lit
Norms and Standards of Nepal for Rate Analysis
1.0 Tree Cutting
| Description | Unskilled Labour | Transport Distance |
|---|---|---|
| Cutting | ||
| ɸ 12-30 cm of girth | 0.13 | 15m |
| ɸ 31-60 cm girth | 0.39 | 15m |
| ɸ 61-120 cm girth | 0.98 | 15m |
| Un-rooting | ||
| ɸ 12-30 cm | 0.40 | 15m |
| ɸ 31-60 cm | 0.52 | 15m |
| ɸ 61-120 cm | 2.52 | 15m |
2.0 Brick Work
Remark: For G.F. (Ground Floor) 0.2, For F.F. (First Floor) 0.7 (additional labour factor by floor level).
| Description | Skilled | Unskilled | Transport | Unit |
|---|---|---|---|---|
| Brick work (1:3) | 1.5 | 2.2 | 30m | cum |
| Brick work (1:4) | – | – | – | cum |
| Brick work (1:5) | – | – | – | cum |
| Brick work (1:6) | – | – | – | cum |
3.0 Stone Work
| Description | Skilled | Unskilled | Transport | Unit |
|---|---|---|---|---|
| Rubble stone masonry (1:3 – 1:6) | 1.5 | 5 | 10m | cum |
| Rubble Arch (1:3 – 1:6) | 2 | 5.4 | 10m | cum |
| Rubble stone masonry (Dry) | 1 | 2 | 10m | cum |
| Broken stone | 1.5 | 3 | 10m | cum |
4.0 PCC Work
| Description | Skilled | Unskilled | Transport | Unit |
|---|---|---|---|---|
| PCC (1:2:4) | 1 | 4 | 30m | cum |
| PCC (1:3:6) | – | – | – | cum |
| PCC (1:4:8) | – | – | – | cum |
| PCC (1:5:10) | – | – | – | cum |
5.0 PCC for RCC Work
| Description | Skilled | Unskilled | Transport | Unit |
|---|---|---|---|---|
| PCC for RCC (1:2:4) | 0.8 | 7 | 30m | cum |
| PCC for RCC (1:1.5:4) | – | – | – | cum |
| PCC for RCC (1:1:2) | – | – | – | cum |
Remark: If Mixture (0.6 hr) + Vibrator (0.25 hr): Skilled 0.5, Unskilled 3.5
6.0 Flooring Work
| Description | Skilled | Unskilled | Unit | Remarks |
|---|---|---|---|---|
| 38 mm thick Punning (1:2:4) | 1.25 | 2 | 10 sqm | – |
| 50 mm thick Punning (1:2:4) | – | 2.25 | 10 sqm | – |
| 75 mm thick Punning (1:2:4) | – | 3 | 10 sqm | TBC |
7.0 Soling Work
| Description | Skilled | Unskilled | Unit | Brick (Nos.) | Cement, C (m³) | Sand, S (m³) |
|---|---|---|---|---|---|---|
| Flat Brick soling (1:6 with pointing) | 2.25 | 3.25 | 10 sqm | 430 | 0.078 | 0.23 |
| Edge Brick soling (1:6 with pointing) | 1.1 | 1.8 | 10 sqm | 750 | 0.121 | 0.43 |
| FBS Dry | 0.5 | 1 | 10 sqm | 420 | – | 0.71 |
| EBS Dry | 1 | 3.25 | 10 sqm | 750 | – | 0.71 |
| Flat stone soling dry | 1 | 3.5 | 10 sqm | 1.1 m³ (stone) | – | 0.71 |
8.0 Plaster Work
| Description | Skilled | Unskilled | Unit |
|---|---|---|---|
| 12.5mm thick cement plaster (1:3 – 1:6) | 12 | 16 | 100 sqm |
| For ceiling | 12 | 20 | 100 sqm |
| 20mm thick cement plaster (1:3 – 6) | 14 | 19 | 100 sqm |
9.0 Sanitary Fixture
| Description | Skilled | Unskilled | Unit |
|---|---|---|---|
| Water closet commode with low level cistern | 3 | 3 | no |
| Water closet pan with low level cistern | – | – | no |
| Wash basin | 2 | 2 | no |
| Kitchen sink | – | – | no |
10.0 Form Work
| Description | Skilled | Unskilled | Transport | Unit | Wood | Nail |
|---|---|---|---|---|---|---|
| FW Column | 3.748 | 5.622 | 30m | 10sqm | 0.07 cum | 2.5 kg |
| FW Beam & slab | 4 | 6 | 30m | 10sqm | 0.07 cum | 2.5 kg |
| FW beam up to 0.3 – 0.8m | 2.67 | 4 | 30m | 10sqm | 0.07 cum | 2.5 kg |
| FW (Trench up to 3m) | 0.5 | 1 | – | 100sqm | 4.16 sqm | 2.5 kg |
| FW (Trench >3m) | 1 | 1.75 | – | 100sqm | 4.16 sqm | 2.5 kg |
11.0 Roofing
| Description | Skilled | Unskilled | Unit | Material |
|---|---|---|---|---|
| CGI 0.75mm thick | 1.1 | 1.25 | 10 sqm | CGI – 12 sqm |
| Slate | 4 | 5 | 10 sqm | Slate – 24 sqm |
| Clay tile | 0.5 | 1.5 | 10 sqm | Clay tile – 127 |
| Clay tile dhuri | 0.5 | 0.5 | 10 rm | Tile – 27 |
12.0 Wood Work
| Description | Skilled | Unskilled | Unit | Wood | H.F. (No.) | Nail |
|---|---|---|---|---|---|---|
| Wooden frame (agrakh) | 34 | 3.4 | cum | 1.1 | 92 | 184 |
| 38mm thick Agrakh Frame with panel (measurement 1.829 x 1.22 = 2.114 sqm) | 10 | 1 | sqm | 0.084 cum | 100mm hinge – 6, 250mm locking set – 1, handle – 2, tower bolt – 2 | nail – L.S. |
13.0 Painting Work
Remark: For ceiling, unskilled labour increased by 25%.
| Description | Skilled | Unskilled | Unit | Paint | Gum / Primer |
|---|---|---|---|---|---|
| Whitewash 1 coat | 0.8 | 0.7 | 100sqm | 12 kg | Gum 0.48 kg |
| Whitewash 2 coat | 1.5 | 1.1 | 100sqm | 22 kg | Gum 0.88 kg |
| Whitewash 3 coat | 3 | 2.7 | 100sqm | 32 kg | Gum 1.28 kg |
| Distemper 1 coat | 4 | 4 | 100sqm | 8 lit | Primer 6.5 kg |
| Distemper 2 coat | 5.8 | 5.8 | 100sqm | 8 lit | Primer 11.5 kg |
| Waterproof paint 1 coat | 1.7 | 1.7 | 100sqm | 30 kg | – |
| Waterproof paint 2 coat | 5 | 5 | 100sqm | 48.5 kg | – |
| Enamel paint 1 coat | 8 | 5 | 100sqm | 9 lit | Primer 8.1 lit |
| Enamel paint 2 coat | 12 | 8 | 100sqm | 16 lit | Primer 8.1 lit |
| Emulsion paint 1 coat | 8 | 5 | 100sqm | 9 lit | Primer 8.1 lit |
| Emulsion paint 2 coat | 12 | 8 | 100sqm | 16 lit | Primer 8.1 lit |
| Aluminium paint 2 coat | 10.75 | 10.75 | 100sqm | 10.76 lit | Primer 8.1 lit |
| Varnish 1 coat | 3 | 2 | 100sqm | 6 lit | – |
| Varnish 2 coat | 6 | 4 | 100sqm | 11 lit | – |
| Chapra polish 3 coat | 10 | 5 | 100sqm | 2 kg | Sprit – 10 lit |
Road Works Norms
| S.N. | Description | Unit | Labour (Class – Qty) | Material (Type – Qty) | Equipment (Type – Qty) |
|---|---|---|---|---|---|
| 1. Preparation of subgrade in ordinary soil cutting: 10m lead | |||||
| i) | Upto 10cm depth | m² | Unskilled 0.12 | – | – |
| ii) | Upto 20cm depth | m² | Unskilled 0.18 | – | – |
| iii) | Upto 30cm depth | m² | Unskilled 0.24 | – | – |
| 2. Preparation of subgrade in stone mixed soil cutting: 10m lead | |||||
| i) | 40-60% stone mixed: upto 10cm depth | m² | Unskilled 0.29 | – | – |
| ii) | 40-60% stone mixed: upto 20cm depth | m² | Unskilled 0.41 | – | – |
| iii) | 40-60% stone mixed: upto 30cm depth | m² | Unskilled 0.53 | – | – |
| 3. Providing & spreading approved size gravel in sub-grade: 10m lead (loose gravel +35%) | |||||
| i) | 10cm thick (compacted) | m² | Unskilled 0.14 | Gravel 0.135 m³ | Road Roller 0.028 hr |
| ii) | 15cm thick (compacted) | m² | Unskilled 0.21 | Gravel 0.203 m³ | Road Roller 0.042 hr |
| iii) | 25cm thick (compacted) | m² | Unskilled 0.32 | Gravel 0.337 m³ | Road Roller 0.070 hr |
| 4. Compaction by 8-10 ton Road Roller | |||||
| i) | Sub Base Course | 100 m³ | – | – | Road Roller 3 hr |
| ii) | Base Course | 100 m³ | – | – | Road Roller 4 hr |
| 5. Providing & laying crushed stone, sand & clay base course (clay bound macadam): 10m lead | |||||
| i) | 6cm compacted thickness | m² | Unskilled 0.10 | Coarse Agg 0.0794 m³, Screening 0.016 m³, B. material 0.007 m³ | Road Roller 0.0024 hr |
| ii) | 7.5cm compacted thickness | m² | Unskilled 0.12 | Coarse Agg 0.10 m³, Screening 0.02 m³, B. material 0.009 m³ | Road Roller 0.003 hr |
| iii) | 10cm compacted thickness | m² | Unskilled 0.13 | Coarse Agg 0.1087 m³, Screening 0.021 m³, B. material 0.0096 m³ | Road Roller 0.0032 hr |
| 6. Providing & laying crushed stone and stone dust (stone bound macadam): 10m lead | |||||
| i) | 6cm compacted thickness | m² | Unskilled 0.10 | Coarse Agg 0.0794 m³, Stone dust 0.016 m³ | Road Roller 0.0024 hr |
| ii) | 10cm compacted thickness | m² | Unskilled 0.15 | Coarse Agg 0.1087 m³, Stone dust 0.0213 m³ | Road Roller 0.0032 hr |
| iii) | 15cm compacted thickness | m² | Unskilled 0.23 | Coarse Agg 0.20 m³, Stone dust 0.04 m³ | Road Roller 0.006 hr |
| 7. Providing & laying Base Course of crushed stone | |||||
| i) | 10cm thick (compacted) | m² | Unskilled 0.15 | 75mm c.stone 0.148 m³ | Road Roller 0.004 hr |
| ii) | 7.5cm thick (compacted) | m² | Unskilled 0.12 | 50mm c.stone 0.10 m³ | Road Roller 0.003 hr |
| 8. Providing & laying Tack coat | |||||
| i) | Over old pitch surface | 10 m² | Unskilled 0.20 | Bitumen 7.3 Kg, Kerosene L.S, Wood (Boiler) 3 Kg, Wood (open area: mass work) 12 Kg, Wood (open area: patch work) 18 Kg | Boiler & sprayer 0.04 hr |
| ii) | Over Base course | 10 m² | Unskilled 0.20 | Bitumen 12.2 Kg, Kerosene L.S, Wood (Boiler) 5 Kg, Wood (open area: mass work) 20 Kg, Wood (open area: patch work) 30 Kg | Boiler & sprayer 0.04 hr |
| 9. Providing & laying priming coat | |||||
| i) | Over old pitch surface | 10 m² | Unskilled 0.20 | Bitumen 4.9 kg, Kerosene L.S, Wood (Boiler) 2 kg, Wood (open mass) 8 kg, Wood (patch work) 12 kg | Boiler & sprayer 0.04 hr |
| ii) | Over Base course | 10 m² | Unskilled 0.20 | Bitumen 9.7 kg, Kerosene L.S, Wood (Boiler) 4 kg, Wood (open mass) 16 kg, Wood (patch work) 24 kg | Boiler & sprayer 0.04 hr |
| 10. Providing & laying single coat surface dressing including compaction | |||||
| – | Single coat surface dressing | 10 m² | Unskilled 0.80 | Bitumen 34 kg, Kerosene L.S, Wood (Boiler) 8 kg, Wood (open mass) 32 kg, Wood (patch work) 48 kg, 12mm Aggregate 0.15 m³ | Roller 0.04 hr, Boiler & sprayer 0.04 hr |
| 11. Providing & laying double coat surface dressing | |||||
| – | Double coat surface dressing | 10 m² | Unskilled 0.80 | Bitumen 34 kg, Kerosene L.S, Wood (Boiler) 13 kg, Wood (open mass) 52 kg, Wood (patch work) 78 kg, 12mm Aggregate 0.18 m³, 10mm Aggregate 0.10 m³ | Roller 0.07 hr, Boiler & sprayer 0.07 hr |
| 12. Providing & semi grouting including compaction | |||||
| i) | 5 cm depth | 10 m² | Unskilled 1.20 | Bitumen 35 kg, Kerosene L.S, Wood 12, 48, 72 kg, 38mm Agg 0.60 m³, 12mm Agg 0.15 m³ | Roller 0.07 hr, Boiler & sprayer 0.07 hr |
| ii) | 10 cm depth | 10 m² | Unskilled 2.00 | Bitumen 60 kg, Kerosene L.S, Wood 20, 80, 108 kg, 38mm Agg & 12mm Agg (quantity not specified in source) | Roller 0.07 hr, Boiler & sprayer 0.07 hr |
| 13. Providing & full grouting including compaction | |||||
| – | Full grouting | 10 m² | Unskilled 1.20 | Bitumen 50 kg, Kerosene L.S, Wood 20, 80, 120 kg, 38mm Agg & 12mm Agg (quantity not specified in source) | Roller 0.07 hr, Boiler & sprayer 0.07 hr |
| 14. Providing & laying seal coat including compaction (with 6mm stone chips) | |||||
| – | Seal coat | 10 m² | Unskilled 0.45 | Bitumen 15 kg, Kerosene L.S, Wood 6, 24, 36 kg, 6mm chips 0.12 m³ | Roller 0.04 hr, Boiler & sprayer 0.04 hr |
| 15. Providing, laying & compaction 40mm thick premixed Asphalt concrete | |||||
| – | Premixed Asphalt concrete | 10 m² | Unskilled 0.45 | Bitumen 9.6 kg, Kerosene L.S, Wood 4, 16, 24 kg, Coarse sand 0.07 m³ | Roller 0.04 hr, Boiler & sprayer 0.04 hr |
Material Rate on the Basis of Government (Ktm – 2071/2072)
| S.N. | Materials / Manpower / Machine | Unit | Rate (Nrs) | Remarks |
|---|---|---|---|---|
| 1 | Skilled labor | no | 650 | – |
| 2 | Unskilled labor | no | 475 | – |
| 3 | Helper | no | 475 | – |
| 4 | Brick (machine made) | no | 10.92 | – |
| 5 | Brick (chimney made) | no | 10 | – |
| 6 | Cement Hetauda-OPC (50 kg) | bag | 743 | – |
| 7 | Cement Udayapur-OPC (50 kg) | bag | 792 | – |
| 8 | White cement (40 kg) | bag | 995 | – |
| 9 | Quarry stone | cft | 56 | 1975.68/cum |
| 10 | River stone | cft | 60 | 2116.8/cum |
| 11 | Quarry sand | cft | 59 | 2081.52/cum |
| 12 | River sand | cft | 62 | 2187.36/cum |
| 13. Aggregates (machine-crusher) | ||||
| 6-10 mm size | cft | 62 | 2187.36/cum | |
| 10-20 mm size | cft | 66 | 2328.48/cum | |
| 20-40 mm size | cft | 68 | 2399.04/cum | |
| 6 mm down | cft | 56 | 1975.68/cum | |
| Man made (all size) | cft | 61 | 2152.08/cum | |
| 14. Base course / sub-base course | ||||
| Gravel | cft | 48 | 1693.44/cum | |
| Stone dust | cft | 28 | 987.84/cum | |
| 15 | Wood (Agrakh) | cft | 5400 | 190512/cum |
| Formwork (mixed) | cft | 1146 | 40430.88/cum | |
| 16. Reinforcement | ||||
| 8mm dia | kg | 82.7 | – | |
| 10-25 mm dia | kg | 79.7 | – | |
| 28mm-32mm dia | kg | 82.55 | – | |
| Binding wire | kg | 94 | – | |
| 17. Paint | ||||
| Whitewash | kg | 17 | – | |
| Distemper | lit | 197 | – | |
| Waterproof paint | lit | 420 | – | |
| Enamel paint | lit | 463 | – | |
| Emulsion paint | lit | 464 | – | |
| Aluminium | lit | 482 | – | |
| Varnish | lit | 389 | – | |
| Chapra polish | kg | 809 | – | |
| Sprit | lit | 104 | – | |
| Primer cement | kg | 236 | – | |
| Wood primer | lit | 332 | – | |
| Gum | kg | 231 | – | |
| 18. Hinge | ||||
| 3″ | no | 15 | – | |
| 4″ | no | 27 | – | |
| 5″ | no | 42 | – | |
| 6″ | no | 55 | – | |
| 19. Locking Set | ||||
| 300mm | no | 252 | – | |
| 225mm | no | 221 | – | |
| 150mm | no | 189 | – | |
| 20 | Tower bolt (3″, 4″, 6″, 8″, 10″, 12″) | no | 20, 39, 65, 78, 91, 103 | – |
| 21. Handle | ||||
| Ordinary | no | 31 | – | |
| Special | no | 46 | – | |
| 22 | Hold fast (7 no/kg) | kg | 121 | – |
| Nail | kg | 109 | – | |
| 23 | 80/100 grade bitumen | kg | 92.6 | – |
| CRMB-DIGO 55 Bitumen | kg | 99.9 | – | |
| Wood | kg | 17 | – | |
| 24 | White glazed porcelain clay 10 lit cistern complete set (internal part of cistern PVC fittings) | set | 3229.2 | – |
| 25. Super Color Porcelain Pan | ||||
| 580mm size | – | 4020 | – | |
| 500mm size | – | 3090 | – | |
| 26 | White glazed porcelain clay EWC floor mounted commode without cistern, all complete set | – | 7854 | – |
| 27 | Porcelain clay white glaze large flat back urinal 61×41×38 cm size | – | 3787 | – |
| 28. Modern Sanitaryware: Mogen, Cotto, Bolan or eqv. | ||||
| Basin Mixture | set | 5000 | – | |
| Commode | no | 13750 | – | |
| Commode seat cover | no | 2200 | – | |
| C.P. 15 mm dia. Angle Valve | no | 1098 | – | |
| C.P. hinge | no | 850 | – | |
| 15 mm C.P. Pillar Cock With Aerator | no | 1115 | – | |
| Flushing pipe | no | 315 | – | |
| Stainless sink | no | 2250 | – | |
| PVC connector | no | 290 | – | |
Rate Analysis Format
| S.N. | Description | Amount |
|---|---|---|
| 1. | Cost of material | X |
| 2. | Cost of labors | Y |
| 3. | Hire of tools and plants (@ 3% of Unskilled labor cost) | Z |
| Sub total (A) = | X + Y + Z | |
| 4. | Contractors overhead and profit @ 15% | = 0.15 A |
| Total (B) = | 1.15 A | |
| 5. | VAT @ 13% of Total (B) | (Option) |
| Grand Total = | Rate per unit | |
Note: Extra cost such as scaffolding for super structure etc. may be provided as a L.S. (lump sum) amount.
Solved Rate Analysis Examples
Volume of brick work = 1.0 m³. Assume brick size = 230mm x 110mm x 55mm; mortar thickness = 10mm; brick size with mortar = 240mm x 120mm x 65mm.
No. of bricks required $= \dfrac{1.0}{0.24 \times 0.120 \times 0.065} = 534.18 \approx 535$ Nos. Add 5% wastage $\therefore$ Brick required $= 1.05 \times 535 = 562$ Nos.
Volume of wet mortar = Total brick work – Actual vol. of brick (without mortar) $= 1 – 534.18 \times (0.23 \times 0.11 \times 0.055) = 0.26\text{ m}^3$
Dry vol. of mortar $= 1.3 \times 0.26 = 0.338\text{ m}^3$. Total part of mix proportion $= 1+3 = 4$.
Required cement $= \dfrac{0.338}{4} = 0.0845\text{ m}^3 = 0.0845 \times 28.8 = 2.434$ bags. Required sand $= 3 \times 0.0845 = 0.2535\text{ m}^3$.
Water cement ratio $= 0.6$; Water $= 0.6 \times 2.434 \times 50 = 73.02$ lit.
Hence, Required: Bricks = 562 no, Cement = 2.434 bag, Sand = 0.2535 m³, Water = 73.02 lit.
| S.N. | Description | Unit | Quantity | Rate (Nrs) | Amount |
|---|---|---|---|---|---|
| 1. Material | |||||
| i) | Cement | bag | 2.434 | 743 | 1808.462 |
| ii) | Sand | cum | 0.2535 | 2187.36 | 554.4958 |
| iii) | Bricks | no | 562 | 10 | 5620 |
| iv) | Water | lit | 73.02 | 0.25 | 18.255 |
| Sub total (A) | 8001.213 | ||||
| 2. Labors | |||||
| i) | Skilled | no | 1.5 | 650 | 975 |
| ii) | Unskilled | no | 2.2 | 475 | 1045 |
| iii) | Helper | no | 0.7 | 475 | 332.5 |
| Sub total (B) | 2352.5 | ||||
| Total (A+B) | 10353.71 | ||||
| 3. Hire of tools and plants @ 3% of unskilled labor | 31.35 | ||||
| Total | 10385.06 | ||||
| 4. Contractors overhead and profit @ 15% of total | 1557.759 | ||||
| Grand Total | 11942.82 | ||||
Hence, Rate per cum = Nrs. 11942.82, excluding VAT
Quantity of plastering work $= 100\text{ m}^2$. Vol. of wet mortar $= 100 \times 0.0125 = 1.25\text{ m}^3$.
Firstly, increase 25% for filling in between joints and irregular surface to get total wet mix $= 1.25 \times 1.25 = 1.5625\text{ m}^3$.
To get dry vol. of mortar, 30% increase: Vol. of dry mortar $= 1.30 \times 1.5625 = 2.031\text{ m}^3$. Total part of mix proportion $= 1+4 = 5$.
Required cement $= \dfrac{1}{5} \times 2.031 = 0.406\text{ m}^3 = 0.406 \times 28.8 = 11.69$ bags. Sand $= 0.406 \times 4 = 1.624\text{ m}^3$.
Water cement ratio $= 0.8$; Water $= 0.8 \times 11.69 \times 50 = 467.71$ lit.
Hence, Required: Cement = 11.69 bag, Sand = 1.624 m³, Water = 467.71 lit.
| S.N. | Description | Unit | Quantity | Rate (Nrs) | Amount |
|---|---|---|---|---|---|
| 1. Material | |||||
| i) | Cement | bag | 11.69 | 743 | 8685.67 |
| ii) | Sand | cum | 1.624 | 2187.36 | 3552.273 |
| iii) | Water | lit | 467.71 | 0.25 | 116.9275 |
| Subtotal (A) | 12354.87 | ||||
| 2. Labors | |||||
| i) | Skilled | no | 12 | 650 | 7800 |
| ii) | Unskilled | no | 16 | 475 | 7600 |
| Subtotal (B) | 15400 | ||||
| Total (A+B) | 27754.87 | ||||
| 3. Hire of tools and plants @ 3% of unskilled labor | 228 | ||||
| Total | 27982.87 | ||||
| 4. Contractors overhead and profit @ 15% of total | 4197.431 | ||||
| Grand Total | 32180.3 | ||||
Hence, Rate per 100 sqm = Nrs. 32180.3, excluding VAT.
Hence, Rate per sqm = Nrs. 321.8, excluding VAT.
Total quantity of work (PCC) $= 1.0\text{ m}^3$. To get dry vol. of concrete mix, increase 50% to 55%: Vol. of dry mix $= 1.5 \times 1.0 = 1.5\text{ m}^3$.
Total part of mix proportion $= 1+2+4 = 7$.
Required: Cement $= 1.50 \times \dfrac{1}{7} = 0.214\text{ m}^3 = 0.214 \times 28.8 = 6.16$ bags. Sand $= 0.214 \times 2 = 0.428\text{ m}^3$. Aggregate $= 0.214 \times 4 = 0.856\text{ m}^3$.
Water/Cement $= 0.55$; Water $= 0.55 \times 6.16 \times 50 = 169.94$ lit.
Hence, Required: Cement = 6.16 bag, Sand = 0.428 m³, Aggregate = 0.856 m³, Water = 169.94 lit.
| S.N. | Description | Unit | Quantity | Rate (Nrs) | Amount |
|---|---|---|---|---|---|
| 1. Material | |||||
| i) | Cement | bag | 6.16 | 743 | 4576.88 |
| ii) | Sand | cum | 0.428 | 2187.36 | 936.1901 |
| iii) | Aggregates | cum | 0.856 | 2399.04 | 2053.578 |
| iv) | Water | lit | 169.94 | 0.25 | 42.485 |
| Subtotal (A) | 7609.133 | ||||
| 2. Labors | |||||
| i) | Skilled | no | 0.8 | 650 | 520 |
| ii) | Unskilled | no | 7 | 475 | 3325 |
| Subtotal (B) | 3845 | ||||
| Total (A+B) | 11454.13 | ||||
| 3. Hire of tools and plants @ 3% of unskilled labor | 99.75 | ||||
| Total | 11553.88 | ||||
| 4. Contractors overhead and profit @ 15% of total | 1733.082 | ||||
| Grand Total | 13286.97 | ||||
Hence, Rate per cum = Nrs. 13286.97, excluding VAT.
Volume of stone masonry $= 10\text{ m}^3$. To get volume of stone, increase by 15% to 20% due to wastage and dressing during placing: Volume of stone $= 10 \times 1.15 = 11.50\text{ m}^3$.
Take volume of dry mortar 30% – 40% of volume of stone masonry due to irregular shape and size of stone available: Vol. of dry mortar $= 40\%$ of work quantity $= 0.4 \times 10 = 4\text{ m}^3$.
Total part of mix proportion $= 1+6 = 7$. Required cement $= \dfrac{1}{7} \times 4 = 0.57\text{ m}^3 = 0.57 \times 28.8 = 16.45$ bags.
Required sand $= 6 \times 0.57 = 3.42\text{ m}^3$. W/C $= 0.6$; Required water $= 0.6 \times 16.45 \times 50 = 493.5$ lit.
| S.N. | Description | Unit | Quantity | Rate (Nrs) | Amount |
|---|---|---|---|---|---|
| 1. Material | |||||
| i) | Cement | bag | 16.45 | 743 | 12222.35 |
| ii) | Sand | cum | 3.42 | 2187.36 | 7480.771 |
| iii) | Stone | cum | 11.5 | 1975.68 | 22720.32 |
| iv) | Water | lit | 493.5 | 0.25 | 123.375 |
| Subtotal (A) | 42546.82 | ||||
| 2. Labors | |||||
| i) | Skilled | no | 15 | 650 | 9750 |
| ii) | Unskilled | no | 50 | 475 | 23750 |
| Subtotal (B) | 33500 | ||||
| Total (A+B) | 76046.82 | ||||
| 3. Hire of tools and plants @ 3% of unskilled labor | 712.5 | ||||
| Total | 76759.32 | ||||
| 4. Contractors overhead and profit @ 15% of total | 11513.9 | ||||
| Grand Total | Nrs. 88273.21 | ||||
Hence, Rate per 10 cum = Nrs. 88273.21, excluding VAT.
Volume of gravel sub-grade $= \dfrac{10}{100} \times 1 = 0.1\text{ m}^3$. Add 30% – 40% to get loose volume of gravel $= 1.35 \times 0.1 = 0.135\text{ m}^3$.
(A) Materials
i. Well graded gravel $= 0.135\text{ m}^3$ @ Rs 1700 = Rs 229.50
(B) Labors
i. Unskilled $= 0.14$ Nos. @ Rs 475 = Rs 66.50
(C) Equipment
i. Road roller $= 0.028$ hr. @ Rs 1000 = Rs 28.00
(D) Hire of tools and plants $= 3\%$ of unskilled labor cost = Rs 2.00
Total = Rs 326.00
(E) Contractor’s overhead and profit $= 15\%$ of Total $= 0.15 \times 326.00 =$ Rs 48.90
Grand total = Rs 326.00 + Rs 48.90 = Rs 374.90
Hence, Rate per sq. meter = Rs. 374.90
Volume $= 0.1 \times 10 = 1\text{ m}^3$. Loose volume $= 1.4 \times 1 = 1.40\text{ m}^3$.
Materials
i. Well graded Aggregates $= 1.40\text{ m}^3$ @ Rs 2100 = Rs 2940.00
ii. Bitumen $= 60$ kg @ Rs 99.00 = Rs 5940.00
iii. Wood (only boiler) $= 20$ kg @ Rs 17.00 = Rs 340.00
Labors
i. Unskilled $= 2$ Nos. @ Rs 475 = Rs 950.00
Equipment
i. Roller $= 0.07$ hr. @ Rs 1000 = Rs 70.00
ii. Boiler and sprayer $= 0.07$ hr. @ Rs 1000 = Rs 70.00
Hire of tools and plants $= 3\%$ of unskilled labor cost = Rs 28.50
Total = Rs 10310.00
Contractor’s overhead and profit $= 15\%$ of Total $= 0.15 \times 10310.00 =$ Rs 1546.50
Grand total = Rs 10310.00 + Rs 1546.50 = Rs 11856.50
Hence, Rate per 10 sq. meter = Rs. 11856.50
Materials
i. 15 mm dia. GI pipe $= 1$ m @ Rs 250 = Rs 250.00
ii. GI fittings (elbow, bend, tee etc.) = L.S (20-30%) = Rs 75.00
iii. Pipe tape, clamp, screws etc. = L.S (5-7%) = Rs 17.50
Labors
i. Skilled $= 0.18$ Nos. @ Rs 650 = Rs 117.00
ii. Unskilled $= 0.16$ Nos. @ Rs 475 = Rs 76.00
Hire of tools and plants $= 3\%$ of unskilled labor cost = Rs 2.28
Total = Rs 537.78
Contractor’s overhead and profit $= 15\%$ of Total $= 0.15 \times 537.78 =$ Rs 80.67
Grand total = Rs 537.78 + Rs 80.67 = Rs 618.45
Hence, Rate per running meter = Rs 618.45
(A) MATERIALS
(i) White glazed ceramic clay W.C commode with P or S-trap = 1 no. @ Rs 7854.00 = Rs 7854.00
(ii) White glazed ceramic clay 10 lit. capacity low level cistern with complete accessories = 1 no. @ Rs 3230 = Rs 3230.00
(iii) Commode cover with C.P hinge = 1 no. @ Rs 2200 = Rs 2200.00
(iv) C.P angle valve (Blue star or equivalent) = 1 no. @ Rs 1098 = Rs 1098.00
(v) PVC pipe connector with coupling = 1 no. @ Rs 290 = Rs 290.00
(vi) 32mm dia. PVC flushing pipe with coupling = 1 no. @ Rs 315 = Rs 315.00
(vii) Pipe tape, clamp, screws etc. = L.S = Rs 600.00
Material cost = Rs 15587.00
(B) LABORS
(i) Skilled: 3 no. @ Rs 650 = Rs 1950
(ii) Unskilled: 3 no. @ Rs 475 = Rs 1425
Labor cost = Rs 3375
(C) Hire of tools and plants @ 3% of unskilled labor cost = Rs 42.75
Subtotal = Rs 19004.75
(D) Contractor overhead and profit @ 15% of subtotal = Rs 2850.71
Total = Rs 21855.46 / no
(A) MATERIALS
White glazed ceramic clay W.C. Orisa pan with P or S-trap = 1 no. @ Rs 3090.00 = Rs 3090.00
White glazed ceramic clay 10 lit. capacity low level cistern with complete accessories = 1 no. @ Rs 3230 = Rs 3230.00
C.P angle valve (Blue star or equivalent) = 1 no. @ Rs 1098 = Rs 1098.00
PVC pipe connector with coupling = 1 no. @ Rs 290 = Rs 290.00
32mm dia. PVC flushing pipe with coupling = 1 no. @ Rs 315 = Rs 315.00
Pipe tape, clamp, screws etc. = L.S = Rs 600.00
Material cost = Rs 11998.00
(B) LABORS
Skilled: 3 no. @ Rs 650 = Rs 1950
Unskilled: 3 no. @ Rs 475 = Rs 1425
Labor cost = Rs 3375
(C) Hire of tools and plants @ 3% of unskilled labor cost = Rs 42.75
Subtotal = Rs 15415.75
(D) Contractor overhead and profit @ 15% of subtotal = Rs 2312.36
Total = Rs 17758.11 / no
(A) MATERIALS
White glazed ceramic clay 500 x 400 size basin = 1 no. @ Rs………….. = Rs…………….
C.P pillar cock = 1 no. @ Rs………….. = Rs…………….
C.P angle valve (Blue star or equivalent) = 1 no. @ Rs………… = Rs……………
PVC pipe connector with coupling = 1 no. @ Rs………….. = Rs…………..
32mm dia. Waste pipe with coupling = 1 no. @ Rs………… = Rs…………….
Pipe tape, clamp, screws etc. = L.S = Rs……………..
Material cost = Rs……………
(B) LABORS
Skilled: 2 no. @ Rs………… = Rs…………..
Unskilled: 2 no. @ Rs………… = Rs…………..
Labor cost = Rs…………….
(C) Hire of tools and plants @ 3% of unskilled labor cost = Rs…………
Subtotal = Rs……………………
(D) Contractor overhead and profit @ 15% of subtotal = Rs……………….
Total = Rs……………… / no
Road Works Rate Analysis Exercises
Rate for Equipments as per fiscal year 073-74 of Ktm:
- Loader = 1910/hr (use 1900/hr)
- Sprayer = 1655/hr (take 1700/hr)
- Boiler = 1757/hr (take 1800/hr)
- Grader = 1498/hr (take 1500/hr)
- Road Roller = 1034/hr (take 1035/hr)
- Bitumen = 77/kg (take 80/kg)
- Wood = 20/kg
Volume of gravel sub-grade $= \dfrac{10}{100} \times 1\text{ m}^2$. Add 30-35% to get loose volume of gravel $= 0.1 + 0.1 \times 0.35 = 0.135\text{ m}^3$.
A) Materials
i) Approved size gravel = 0.135 m³ × Rs…………./m³
B) Labours
i) Unskilled = 0.14 nos. × Rs. 635 per head per day = Rs…………
C) Equipments
i) Road Roller = 0.028 hr × Rs…….. = Rs………..
D) Contractor’s overhead and profit = 15% of (A+B+C) = Rs…………
$\therefore$ Rate per m² = Rs…………..
i) Vol. of base course $= \dfrac{10}{100} \times 1\text{ m}^2 = 0.1\text{ m}^3$
ii) Add 45-48% to get loose vol. of crushed stone $= 0.1 + \dfrac{48}{100} \times 0.1 = 0.148\text{ m}^3$
A) Materials
i) 75 mm size crushed stone = 0.148 m³ × Rs. ……… = Rs……………
B) Labours
i) Unskilled = 0.15 nos. × Rs. 635 per head per day = Rs………………..
C) Equipments
i) Road Roller = 0.04 hr × Rs…………….. per hour = Rs………………….
D) Contractor’s overhead and profit = 15% of (A+B+C) = Rs………………
$\therefore$ Rate per m² = Rs (A+B+C+D)
Vol. of 5 cm thick full grouting $= \dfrac{5}{100} \times 10 = 0.5\text{ m}^3$. Add 45-50% to get loose volume $= 0.5 + 0.5 \times 0.5 = 0.75\text{ m}^3$.
A) Materials
i) Bitumen = 50 kg × Rs……………../kg
ii) Kerosene (Lumpsum) = Rs. 100
iii) Wood (20 kg for boiler, 80 kg for open field, 120 kg for patch repairing) × Rs.20 = Rs. 400
B) Labours
i) Unskilled = 1.2 nos. × Rs. 635/head/day = Rs………….
C) Equipments
i) Roller = 0.07 hr × Rs 1035 per hour = Rs. ……………..
ii) Boiler = 0.07 hr × Rs. 1800 per hour = Rs………………
iii) Sprayer = 0.07 hr × Rs. 1700 per hour = Rs……………
Total = Rs…………………
D) Contractor’s overhead and profit = 15% of (A+B+C) = Rs…………
$\therefore$ Rate per 10 m² = Rs……………….
PDF Notes: Analysis of Rate
Advertisement
Also Read Other Subjects
Disclaimer
The educational materials provided on this website are intended as supplementary resources to support your learning journey in Estimating and Costing and other civil engineering fields. These study materials reference standard curricula from Pulchowk Campus, IOE, TU.
We have made every effort to ensure the accuracy of the content. However, we recommend students to refer to standard textbooks and consult with professors for authoritative explanations. These materials should be used as references only.
We respect intellectual property rights. If you believe any content should be credited differently or removed, or if you are the author and wish for these notes to be removed, please don’t hesitate to contact us. We are happy to make appropriate corrections or give proper attribution.
